Consultancy Service for Detailed Design & Supervision of Access Road Construction Component of Matarbari Ultra Super Critical Coal-Fired Power Project.


Consultancy Service for Detailed Design & Supervision of Access Road Construction Component of Matarbari Ultra Super Critical Coal-Fired Power Project.

  • Country: Bangladesh
  • Client: Roads & Highways Department (RHD)
  • Funding Source: JICA
  • Duration: 4.6 Years
  • Status: In Progress

Project Description

The access road component comprising of about 37 km access road construction from Chittagong –Cox’s Bazar National Highway to Matarbari plant site and 6.5 km long another new access road construction from Mohori  Guna to Rajghat. The component mainly consists of new construction of about 10.5 KM road, rehabilitation of about 12.8 km road, repair of about 20.55 Lm road, construction of an approximately 640 meter pre-stressed concrete Bridge and 2 jetties.

The alignment of 37 Km 1st access road goes sequentially through Ekata Bazar 9about 93 km from Chittagong  of Chittagong –Cox’s Bazar road N1), Pekua Bazar, Eidmoni intersection, Janata Baazar, Yunuskhali Bazar and the power plant crossing the river Kohelia and 2nd access road goes from Mohori Guna to Rajghat.

 

Our Services

  • 1. Field survey and investigations
  • 2. Detailed design of bridges
  • 3. Geometric and pavement design of road
  • 4. Preparation of specification, test procedure manual and estimate
  • 5. Preparation of prequalification, Bidding and contract documents
  • 6. Preparation of resettlement action plan and detailed acquisition maps
  • 7. Environmental management
  • 8. Construction supervision